Project Commenced: The Crown Works

The below article provides an update on our progress on The Crown Works project, which we recently secured.

We are delighted to announce the commencement of our works to the prestigious “Crown Works” project, located in Hanley Street, Birmingham. 

We’re pleased to reveal that our much anticipated Waterproofing Works have now started to the Upper Ground Floor Podium Deck. 

Following some project re-programming, we are waterproofing the 1,200sqm Podium Deck prior to the other floors being cast. 

Let’s hope for some clement weather!

 

Acknowledgements

Information on Graham Group can be found here.

Information on the Sika Promelt waterproofing system can be found here.